SkyTran Structural Posts 
Foundation preparation, installation, attachment and alignment
procedures
Using basic semi-automation construction techniques, we have determined that it will take less than $2,000 per pole installation - including all material components and labor.

W_BP_Pole_drill.GIF (4092 bytes) Step 1: Hydraulic auger drills post hole.
W_BP_Pole_rebar.GIF (5180 bytes)  

 

Step 2: Rebar preform with structural extension studs is placed in hole.

W_BP_Pole_concrete.GIF (5373 bytes)  

 

Step 3: Concrete is added.

W_BP_Pole_install.GIF (5156 bytes)  

 

Step 4: Prefab pole lifted in place, then aligned to vertical and secured to four studs with adjustment nuts. (Single crane operator has remote control of boom extension, boom lift angle and boom swivel with small joystick attached to his belt.)

W_BP_Pole_crossbrace.GIF (6621 bytes)  

 

Step 5: Cross brace for roll formed track installed and laser aligned

Much more to come!