SkyTran Structural Posts 
Foundation preparation, installation, attachment and alignment
procedures
Using basic semi-automation construction techniques, we have determined that it will take less than $2,000 per pole installation - including all material components and labor.

Step 1: Hydraulic auger drills post hole.
 

 

Step 2: Rebar preform with structural extension studs is placed in hole.

 

 

Step 3: Concrete is added.

 

 

Step 4: Prefab pole lifted in place, then aligned to vertical and secured to four studs with adjustment nuts. (Single crane operator has remote control of boom extension, boom lift angle and boom swivel with small joystick attached to his belt.)

 

 

Step 5: Cross brace for roll formed track installed and laser aligned

Much more to come!